Pvt transcos to increase efficiency, attract foreign investment: Pratik Agarwal

The government has said it would tender out power transmission projects worth Rs 1 lakh crore in a year. This has cheered the private entities, for which the market was opened in 2010 through Tariff Based Competitive Bidding (TBCB). The project share, however, had favoured state-owned Power Grid Corporation, which the government now says will […]

SYSTEM AVAILABILITY

Projects DEC 2019 Availability since COD
ENICL 99.82 99.54
BDTCL 99.90 99.71
JTCL 100.00 99.54
RTCL 100.00 99.84
PKTCL 100.00 99.93
NRSS-XXIX 98.61 99.67
MTL 100.00 99.95
OGPTL 100.00 99.95
PTCL 100.00 99.94
KTL 100.00 100.00
GPTL 99.81 99.60

FEEDBACK

    FEEDBACK