Sterlite Power commissions first project in Brazil

According to the statement, the company began construction work on Arcoverde project in May 2018. Sterlite Power Wednesday said it has delivered first power transmission project in Brazil 28 months ahead of schedule. “Sterlite Power celebrates the kickoff of operations in the Arcoverde project. This is the first of 10 projects assigned to the company […]

Sterlite Power delivers its first project in Brazil 28 months ahead of schedule.

Sterlite Power delivers its first project in Brazil 28 months ahead of schedule. Arcoverde Project covers 139 km of power lines and three substations to boost wind energy power transmission in the Pernambuco region. Sterlite Power celebrates the kickoff of operations in the Arcoverde project today, May 9th, 2019, in Pernambuco. This is the first […]

SYSTEM AVAILABILITY

Projects DEC 2019 Availability since COD
ENICL 99.82 99.54
BDTCL 99.90 99.71
JTCL 100.00 99.54
RTCL 100.00 99.84
PKTCL 100.00 99.93
NRSS-XXIX 98.61 99.67
MTL 100.00 99.95
OGPTL 100.00 99.95
PTCL 100.00 99.94
KTL 100.00 100.00
GPTL 99.81 99.60

FEEDBACK

    FEEDBACK