In the three regions of Africa, the Indian subcontinent and South America the way in which millions still access and consume electricity leaves much to be desired. Reliable power supply 24×7 continues to remain a challenge and thousands of households are having to invest in power back-up options.
At Sterlite Power, we believe that universal, reliable and affordable electrification is as much a fundamental right as is its access. As a leading global developer of power transmission infrastructure, we bid, design, construct, own and operate power transmission assets across multiple geographies. We are entrusted with the critical infrastructure that powers economies. We are operational in India and Brazil with a portfolio of 25 projects now, spanning close to 13,700 ckm of transmission lines. Developing, operating and owning these assets provide the foundation for the better world of energy that we strive for.
We are consistently striving towards delivering innovative solutions to age-old problems faced in project development, just as we have been doing in other aspects of a transmission project’s lifecycle. We strongly believe that innovation and sustainability go hand-in-hand and when implemented strategically, it can enhance competitive advantage for businesses.
With the recent commissioning of India’s first vertical GIS substation built as part of the Gurgaon Palwal Transmission project, along with implementation of multi-circuit monopole towers for transmission lines, we managed to save as much as 75% on land usage. This helped us in preserving the region's forests to a large extent. Apart from saving land, these innovations have resulted in offsetting more than 18,000 tonnes of CO2 emissions each year, as compared to a conventional layout for a similar GIS substation.
In a similar vein, a prime example of multi-competency’s collaboration emerged with the successful deployment of a newly designed product that enables critical clearance for long spans. The newly developed ACCC ULS Ganga was utilised at one of India’s longest river crossings across River Ganga, at the Purnia Bihar Sharif transmission line, at a span of ~1.1 km.
25 power
transmission projects
won under Public-Private Partnerships (PPP); 15 in India under TBCB and 10 in Brazil
~26,100 MVA
of transformation capacity~13,700 ckm
of power transmission lines commissioned or under construction9 operational assets
won under PPP
21 substations
31.5% market share
by tariff of inter-state projects awarded under competitive bidding in India
`36,022 Crore of capex
(US$ 4.88 Billion planned and incurred)
68 EHV transmission lines
99.84% availability
achieved across our commissioned assets in FY 2019-20
Our assets are in strategically important areas from the perspective of transmission connectivity, transferring power from generating centres to load centres to meet inter-regional power deficits. We now have a total portfolio of 15 transmission projects in India, spanning more than 9,000 ckm, through a total capex of `25,262 Crore (US$ 3.42 Billion).
We made significant progress towards our strategic priorities in the last year, chief of which is being declared the winning bidder for three new projects – the Transmission System for Lakadia – Vadodara Transmission Project, the Transmission System for Udupi-Kasargode, the WRSS-XIX and NERSS-IX transmission project. All three projects are unique and true to our core purpose of ‘Empowering Humanity by addressing the toughest challenges of energy delivery’.
Western Region Strengthening Scheme - XIX (WRSS-XIX) and North Eastern Region Strengthening Scheme - IX (NERSS-IX)
This project aims at strengthening the transmission system in western and north-eastern regions of India. It seeks to address decongestion of corridors, along with the delivery of power to high habitation and industrial zones. The project will cover the Vapi area in Gujarat and Navi Mumbai in Maharashtra in the West, while in the North East, it intends to supply power from Pare Hydro Electric Plant to far-flung areas of Arunachal Pradesh.
The project elements include transmission lines at various voltage levels and a GIS substation at Vapi. It encounters severe Right of Way (RoW) constrained zones in Gujarat and Maharashtra. It also faces the challenge of navigating a major forested area in the North East.
Lakadia – Vadodara Transmission Project (LVTPL)
The second project, Lakadia – Vadodara Transmission Project (LVTPL) is part of the Western Region Strengthening Scheme – XXI (WRSS XXI) Part B, which intends to connect Lakadia to Vadodara in Gujarat, to enable evacuation of RE. The project comprises more than 650 ckm of 765 kV transmission line. This project is part of India’s GEC and will enable the country’s RE target of achieving 175 GW renewable energy (RE) by 2022.
Udupi Kasargode Transmission Project (UKTL)
This project will take place in Karnataka and Kerala and aims at system-strengthening and power supply to urban areas of Kerala. The project comprises a GIS substation at Kasargode in Kerala and a 400 kV transmission line. We face the challenge of RoW in this project as well.
WRSS-XIX and NERSS-IX intends to supply power from Pare Hydro Electric Plant to far-flung areas of Arunachal Pradesh
Target of achieving 175 GW RE by 2022
Jabalpur Transmission Company Limited (JTCL)
1 x 765 kV D/C lines
1 x 765 kV S/C lines
Commissioned
994 ckm
Bhopal Dhule Transmission Company Limited (BDTCL)
4 x 765 kV S/C lines
2 x 400 kV D/C lines
4 x 1,500 MVA,
1 x 765/400 kV substation
Commissioned
945 ckm
6,000 MVA
Rapp Transmission Company Limited (RTCL)
1 x 400/220 kV D/C line
Commissioned
402 ckm
Maheshwaram Transmission Company Limited (MTCL)
2 x 400 kV D/C lines
Commissioned
472 ckm
Purulia & Kharagpur Transmission Company Limited (PKTCL)
2 x 400 kV D/C lines
Commissioned
545 ckm
NRSS XXIX Transmission Limited (NRSS)
3 x 400 kV D/C lines
1 x 400/220 kV D/C GIS
Commissioned
830 ckm
735 MVA
East-North Interconnection Company Limited (ENICL)
2 x 400 kV D/C lines
Commissioned
904 ckm
Gurgaon – Palwal Transmission Limited (GPTL)
5 x 400 kV D/C lines
3 x 400/220 kV substation
Commissioned
271 ckm
3,000 MVA
Khargone Transmission Limited (KTL)
2 x 765 kV D/C lines
1 x 400 kV D/C line
1 x 765/400 kV substation
June, 2020
622 ckm
3,000 MVA
NER II Transmission Limited (NER-II)
2 x 400 kV D/C line
3 x 132 kV D/C line
2 x 400/132 kV substation
November, 2020
832 ckm
1,260 MVA
Odisha Generation Phase-II Transmission Limited (OGPTL)
1 x 765 kV D/C line
1 x 400 kV D/C line
Commissioned
710 ckm
Goa – Tamnar Transmission Project Limited (GTTPL)
1 x 765 kV D/C line
1 x 400 kV D/C line
1 x 400/220 kV substation
November, 2021
478 ckm
1,000 MVA
Lakadia – Vadodara Transmission Project Limited (LVTPL)
1 x 765 kV D/C line
December, 2020
659 ckm
1,000 MVA
Due to impact of the outbreak and spread of COVID-19 pandemic, all under-construction Transmission projects were granted a 5-month extension by Ministry of Power Notification No. 3/1/2020-Trans dated 27-Jul-2020
Udupi Kasargode Transmission Limited (UKTL)
1 x 400 kV D/C line
1 x 400/220 kV substation
November, 2022
231 ckm
1,000 MVA
Western Region Strengthening Scheme - XIX and North Eastern Region Strengthening Scheme - IX (WR-NER)
4 x 400 kV D/C line
2 x 220 kV D/C line
2 x 132 kV D/C line
1 x 400/220 kV substation
December, 2023
351 ckm
1,000 MVA
Our assets are located in strategically important areas from the perspective of transmission connectivity, transferring power from generating centres to load centres to meet inter-regional power deficits. We now have a total portfolio of 15 transmission projects in India, spanning 9,246 ckm, through a total capex of `25,262 Crore (US$ 3.42 Billion).
Footprint in India
4,500 km
ROUTE LENGTH
9,246 ckm
LENGTH
`25,262 Crore
(US$ 3.42 Billion)
PROJECT CAPEX
This map is a graphical representation designed for general reference purposes only
We commissioned our first project in Brazil and that too, 28 months ahead of schedule, while also emerging as winner in the auction of the prestigious Pampa project. In a short span of time, we have developed a portfolio of total 10 transmission projects in the fast-growing South American nation, spanning 4,416 ckm, through a total capex of `10,760 Crore (US$ 1.46 Billion).
Arcoverde
2 x 230 kV transmission line
1 x 230/69 kV substation
August, 2021
129 ckm
400 MVA
Vineyards
3 x 230 kV transmission line
2 x 230/69 kV substation
August, 2022
115 ckm
496 MVA
Novo Estado
3 x 500 kV transmission line
March, 2023
1,831 ckm
Dunas
2 x 500 kV transmission line
3 x 230 kV transmission line
2 x 500/230 kV substation
1 x 230/69 kV substation
September, 2023
541 ckm
3,300 MVA
Borborema
1 x 500 kV transmission line
1 x 500/230 kV substation
March, 2023
129 ckm
750 MVA
São Francisco
2 x 500 kV transmission line
1 x 230 kV transmission line
September, 2023
521 ckm
Goyaz
1 x 230 kV transmission line
March, 2023
152 ckm
600 MVA
Marituba
1 x 500 kV transmission line
March, 2023
374 ckm
Solaris
1 x 345 kV transmission line
1 x 230 kV transmission line
1 x 500/230 kV substation
January, 2024
298 ckm
800 MVA
Pampa
2 x 525 kV transmission line
1 x 525/230 kV substation
March, 2023
326 ckm
1,768 MVA
We commissioned our first project in Brazil in the reporting year, while also emerging as the winner in the auction of the prestigious Pampa project. In a short span of time, we have developed a portfolio of total 10 transmission projects in the fast-growing South American nation, spanning 4,416 ckm, through a total capex of `10,760 Crore (US$ 1.46 Billion)
Footprint in Brazil
2,967 km
ROUTE LENGTH
4,416 ckm
LENGTH
`10,760 Crore
(US$ 1.46 Billion
PROJECT CAPEX
*Assets managed by third party
This map is a graphical representation designed for general reference purposes only
Our projects in Brazil are based on trust, relationship and a synchronised effort made by the environmental bodies and regulatory agencies involved in the environmental licensing process. All environmental licensing processes go through a wide range of discussion with several agencies. This enables us to design projects of high environmental quality, which is well received by the regulators, the society and the communities.
In 2019, we conducted 41 such processes: 16 with environmental licensing agencies; 19 with archaeological and historical heritage agency, four with Quilombola communities* agencies and two with the bodies responsible for health^ in the Legal Amazon region.
We understand that access to information about our projects is an important tool to build and maintain a good relationship with the communities in the regions we operate. Bearing in mind that throughout a linear enterprise, different social and institutional groups are present, with different causes and interests, we felt it necessary to implement mechanisms that facilitate the conduct of the interaction process between the Company and the various social factors. This is embodied in our social communication process, an open dialogue with the communities, which is understood as a systematic and permanent process of information on topics of different interests associated with the changes arising from the implementation of the project, occurring before and during its installation.
The social communication process aims at establishing actions to minimise the effects of implementing the project for the communities directly or indirectly affected by the project. This is achieved by promoting integration between the community and the Company, through a process based on participation, transparency and information. Finally, it also serves as an important foundation for social and environmental plans and programmes, facilitating the provision of information and disseminating its results.
In the Arcoverde project, located in the state of Pernambuco, besides utilising the above communication channels, face-to-face contacts with all landowners and communities affected by our project were made (including a ~130 km long transmission line, two substations, a greenfield and an extension). From these channels a short number of calls were made to our ombudsman, related to taxes, technical aspects, appreciation, among others, all well addressed. This reinforces our good relationship and transparency with the communities.
*ethnic groups, predominantly made up of rural or urban black population, descendants of former slaves
^to develop actions to prevent and avoid malaria among workers and communities at municipalities where the projects are located
Vegetation suppression is important in the stages of installation and operation of power transmission lines. Given this, we developed programmes and procedures with customised techniques for each situation, type of vegetation and region. The established techniques are focused on the safety of forestry operations, excellence and minimisation of the environmental impacts resulting from the intervention.
23.14 Ha
Area in Arcoverde preserved
In the Arcoverde project, applying such best practices in the vegetation removal activity was relevant in reducing the suppression. Also, in the Permanent Preservation Areas (which refer to the mandatorily protected areas that serve the environmental functions of preserving water resources, the landscape, geological stability, biodiversity and the genetic flow of fauna and flora; protecting the soil; and ensuring the safety of the local population), the installation of towers or vegetation suppression was not carried out. This was in addition to the adoption of non-interventional construction techniques in these areas.
We achieved similar results in the Vineyards project as well. In regions with better preserved vegetation, construction activities were customised. Specific practices, such as the use of Unmanned Aerial Vehicles (UAVs) for laying cables conductors in 12 spans of towers and the installation of 349 beacons to avoid the collision of birds with overhead cables in 3.49 km of transmission line, were adopted to reduce negative impact on vegetation. The vegetation suppression activities in the Vineyards project are not yet finalised. However, up to the present moment, the gains are significant if we compare the volume authorised by the environmental agency for the suppression of native vegetation with the volume executed so far; even considering the missing reports. Currently, the reduction is 24.86% compared with the authorised one, the volume of which is 5,984.76 m3.
Forest replacement is a key offsetting activity for direct and indirect impacts on flora; both associated with the installation and the operation of projects. We seek to adopt the best procedures and techniques to manage the forest replacement and the maintenance of genetic and ecological resources.
In Arcoverde, the compensation for vegetation removal occurs in two different types of vegetation, Atlantic Forest and Caatinga – two of the most diverse and thus important biomes in the country and in the world. In the Atlantic Forest area, 1,112 native tree seedlings were planted, including 15 species that play important ecological functions for that biome. Planting was carried out in a biological reserve, in partnership with the municipality of Bonito, in the state of Pernambuco. This biological reserve protects the watershed that supplies the municipality. In the Caatinga region, 5,555 native tree seedlings were planted in an area of relevant interest for the conservation of the local biome. For both forest areas, plantations will be maintained for four years or until they are able to develop without maintenance.
In Vineyards, the compensation for vegetation suppression will be in the Atlantic Forest typology. The following offsetting programmes are so far planned: allocating 7.78 ha of Atlantic Forest, recomposing 0.88 ha of Permanent Preservation Areas; recomposing 1.31 ha of Legal Reserve Areas (which refer to the area of the rural property that must be covered by natural vegetation).
Delivered our first project in Brazil—Arcoverde —28 months ahead of schedule
Arcoverde project covers 139 km of transmission lines and three substation to boost Wind Energy power transmission in the Pernambuco region. The elements within the Arcoverde project expand coverage in the Pernambuco outback region, reinforce the system and cover the growing power demand in the region.
Global recognition for safety in the sector
Received the 'Safety in Electricity Award' in Gold category at the Protection Brazil Awards 2019 for the use of drones and other technologies in crossing energised transmission lines.
India is home to some of the world’s fastest growing cities. Urbanisation and development are triggering exponential demand for power, resulting in transmission congestion challenges. There is an urgent need to strengthen, upgrade and uprate corridor intensity of ageing transmission infrastructure with imaginative, innovative and cost-effective solutions.
Our custom-built solutions, top of the line technological prowess, engineering expertise, system design and specialised EPC services are clear value differentiators. We are India's first and largest integrated manufacturers of OPGW. Creative problem-solving, strategic investments and industry-leading research and development are inextricably tied to our long-standing commitment to customers. Since inception, we have been answering the questions of today to meet the energy needs of tomorrow. That tradition of out-of-the-box thinking continues, as we strive constantly to refine operations and deliver best-in-class customer service. We are innovating on multiple fronts to build the future of energy and address customer challenges swiftly and efficiently through the unwavering prism of time, space and capital.
A full service operation, our MSI business delivers multi-fold increase in throughput, upgrades to existing infrastructure, uprate of overhead conductors and OPGW-based communication systems in the shortest possible time.
Capabilities
Differentiators
KERALA INTERSTATE CORRIDOR TANSFORMATION
Massive uprate/upgrade exercise to revamp the inter-state transmission network with 15-24 times increase in throughput
GANGA RIVER CROSSING PROJECT – BIHAR
Longest span on 400 kV line with HPC (quad configuration)
BRINGING RELIABLE & QUALITY POWER TO DELHI
Over last few years, Delhi has uprated ~50% of its 220kV network with a view to have a ‘Zero generation scenario’ grid plan and rely on imported power. The city will also now have to gear up for upgrade of its substations and lines on critical corridors. Sterlite Power has partnered with Delhi in this transition with execution of ~80% of the uprate projects.
3,500+ ckm
Of uprate and upgrade to existing transmission line (completed or under execution)
90
Critical corridors in 15 states
26,000 km+
OPGW-based communication projects under live-line condition (completed or under execution)
This map is a graphical representation designed for general reference purposes only
INTELLIGENT GRID MONITORING CONTROL
Dynamic Line Rating (DLR) and smart valves will enable utilities to assess in real time and control power flows
SKYROBTM
Robotics technology to ensure safety of ‘high-risk’ operations, involving installation, inspection and maintenance of OPGW on high-voltage transmission lines
AERIAL TECHNOLOGY
Drones for stringing conductors on transmission lines for safety, speed and tough terrains
Overhead Products Business
CONDUCTORS
OPTICAL GROUND WIRE (OPGW)
Underground Products and Turnkey Business
CABLES & SOLUTIONS
Network covers
94
Districts
393
Towns
6,816 km
Of OPGW
Digital connectivity has high correlation with economic growth. A recent report published by the Indian Council for Research on International Economic Relations (ICRIER) found that 'a 10% increase in internet subscribers in India results in a 3.2% increase in the rate of growth of state per capita GDP and a 10% increase in India's mobile internet traffic delivers on an average a 1.6% increase in the national GDP'.
With 5G technology around the corner and IoT devices ready to connect and interact with one another – Machine to Machine (M2M), reliable optical fibre infrastructure is the need of the hour. The omnipresent utilities network located across the length and breadth of the country is poised to address the above need. Fibre network riding on utilities’ existing network can provide unparalleled coverage, along with robust and secured infrastructure.
The National Digital Communication Policy (NDCP) 2018 released by the Government of India outlines the vision of ‘Fibre First Initiative’ to take fibre to homes, enterprises and key development institutions. The policy emphasises how leveraging existing assets of power sector can improve data connectivity. Aligned with the above vision, Convergence business looks at the potential of utilising existing assets of utilities for telecommunication purposes, thereby delivering lasting social impact.
We leverage our transmission infrastructure and other power utilities to roll out a pan-India reliable and efficient OPGW fibre network. This network is far superior compared to the conventional underground counterparts; which faces frequent damages on account of continuous road expansion, utility construction and maintenance and high terrestrial interventions.
We also support cities, which are fast evolving to be ‘smarter’. where urban planners aim to create a citizen-friendly digital ecosystem with critical infrastructure in place. Our smart city fibre solution addresses the communication infrastructure challenges and proposes innovative PPP models. We offer favourable long-term partnership to design, build, finance, operate and maintain an optical fibre network, which can act as the digital backbone for all smart infrastructure in the city.
The aim of the Convergence business is ‘to be the best-in-class communications infrastructure and solutions provider by creating the most reliable network’.
Dark fibre solutions
Reliable, Efficient & Scalable
Colocation solutions
Space, 24X7 support & Multiple Power backups
Convergence business provides a win-win partnership for Smart Cities to design, build, finance, operate and maintain fibre infrastructure on a long-term partnership model.
FIRST OF ITS KIND PPP IN INDIA WITH GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY (GMDA)
Gurugram is one of the first cities where Convergence business has invested and created a world-class optical fibre infrastructure for supporting current and future applications of the city. Sterlite Power has built a network of 133 km in Gurugram and will manage and maintain the network for 21 years.
GMDA: Quick Facts
FY 2019-20 has been a transformational year for the Convergence business for more reasons than one. We embarked on a journey to provide end-to-end data network solutions, expanded market presence and acquired new customer segments. The year ended with highest-ever order booking value of `50 Crore (US$ 6.8 Million), with 100% growth from `23 Crore (US$ 3.1 Million) clocked in the previous financial year.