Arcoverde

Expansion for the assistance to the agreste of Pernambuco.

PROJECT STORY

The Arcoverde Project has 139 km of transmission line to be built, the implementation of 1 new substation and the expansion of some substations in the region to be deployed in the state of Pernambuco. Power of 400 MVA.

Keeping up with with our reputation of commissioning projects ahead of schedule, the Arcoverde project has been commissioned way ahead of is scheduled COD.

Project Detail

Consisting of the following facilities in the state of Pernambuco:

– TL 230 kV Garanhuns II – Arcoverde II, with 89 km;

– TL 230 kV Caetés II – Arcoverde II, with 50 km;

– SE 230/69 kV Arcoverde II – 2 x 100 MVA;

– SE 230/69 kV Garanhuns II – new courtyard 69 kV – 2 x 100 MVA;

TIMELINES

Preliminary Environmental license

Installation Environmental license

Project commissioned ahead of schedule.

PROJECT GALLERY

RELATED PROJECTS

Gurgaon-Palwal Transmission Project (GPTL)

Jabalpur Transmission Project (JTCL)

DISPONIBILIDADE DO SISTEMA

NOME DO PROJETOMARCH 2018DISPONIBILIDADE DESDE COD
ENICL99.6299.67
BDTCL99.4199.87
JTCL98.5499.77
RTCL99.0799.86
PKTCL99.9699.98
NRSS-XXIX98.4799.74
MTL100.0099.98
OGPTL100.00100

FEEDBACK

    FEEDBACK