Novo Estado

This project is the expansion of North-Southeast and North-Northeast interconnections. This is a part of the Belo Monte HPP energy flow solution.

PROJECT STORY

The Novo Estado Project has 1831 km of transmission lines to be built, the implementation of 1 new substation and the expansion of some substations in the region to be deployed in the state of Pará and Tocantins.

This project is expected to generate 5.560 direct / indirect jobs.

Project Detail

Length: 1,831 km
Power: 230 kv

TIMELINES

Preliminary Environmental license
Installation Environmental license

PROJECT GALLERY

RELATED PROJECTS

Arcoverde

Gurgaon-Palwal Transmission Project (GPTL)

DISPONIBILIDADE DO SISTEMA

NOME DO PROJETOMARCH 2018DISPONIBILIDADE DESDE COD
ENICL99.6299.67
BDTCL99.4199.87
JTCL98.5499.77
RTCL99.0799.86
PKTCL99.9699.98
NRSS-XXIX98.4799.74
MTL100.0099.98
OGPTL100.00100

FEEDBACK