According to the statement, the company began construction work on Arcoverde project in May 2018.

Sterlite Power Wednesday said it has delivered first power transmission project in Brazil 28 months ahead of schedule. “Sterlite Power celebrates the kickoff of operations in the Arcoverde project. This is the first of 10 projects assigned to the company in Brazil,” a company statement said. 

According to the statement, the company began construction work on Arcoverde project in May 2018. The project boasts 400 MVA in power, covers 139 km of transmission lines, 281 towers and a new substations in the region

The project’s capital expenditure is estimated by Brazilian Electricity Regulatory Agency, ANEEL at 164 million Brazilian real (over Rs 280 crore). It will generate annual permitted revenue of 24.6 million Brazilian real. 

“This is an important milestone for us. We are confident about our operations in Brazil and for delivering the first project 28 months ahead of the schedule set by ANEEL,’ said Rui Chammas, CEO of Sterlite Power in Brazil. 

Read More: The Economic Times

RELATED PRESS RELEASE

Interview with Manish Agarwal – “Sterlite Power has set new industry benchmarks”

Bottleneck in transmission is opportunity, says CEO of Sterlite

Sterlite Power eyes ₹70,000 crore of renewable energy transmission projects

SYSTEM AVAILABILITY

Projects DEC 2019 Availability since COD
ENICL 99.82 99.54
BDTCL 99.90 99.71
JTCL 100.00 99.54
RTCL 100.00 99.84
PKTCL 100.00 99.93
NRSS-XXIX 98.61 99.67
MTL 100.00 99.95
OGPTL 100.00 99.95
PTCL 100.00 99.94
KTL 100.00 100.00
GPTL 99.81 99.60

FEEDBACK

    FEEDBACK