Sterlite Power and Vinci Partners announce a strategic partnership in the power transmission sector for the purchase of Vineyards Project

  • Sterlite Power’s Vineyards Project, which is already 95% complete and is partially operational with 70% RAP since January 2020, has 112 km of transmission lines, two new substations of 496 MVA, and expansion of four substations in the regions of Garibaldi, Bento Gonçalves, Lajeado, and Bagé.
  • The Project will increase electricity availability by 67%, ensuring better reliability in the local system, characterized by high demand due to industrial activity.

New Delhi, 15 April 2021: Sterlite Power, a leading developer of power transmission infrastructure in India and Brazil, and Vinci Energia (VIGT11), through Vinci InfraestruturaGestora de Recursos LTDA, announced the formalization of the commitment of first acquisition of issuance of debentures convertible into shares for the Vineyards Project that is in the final phase of implementation.

The transaction under this relevant fact foresees R$ 149 million in debentures aimed at developing projects in Sterlite Power’s portfolio. The investment amount can be converted into shares with an 80% purchase option when the Project is complete in this year. The remaining 20% can be purchased within 190 days.

With an initial investment of R$ 395 million, the Vineyards Project includes the construction of 112 km of transmission lines, implementation of two new 496 MVA substations, and the expansion of four substations in the regions of Garibaldi, Bento Gonçalves, Lajeado, and Bagé. A previous debenture issue was held in 2019 when R$250 million was raised. The contract also gives way for the parties to negotiate for more projects in Sterlite Power’s portfolio.

“This partnership is an important recognition for our operations in Brazil since last four years and our long-term plan in the country. We understand that Vinci has identified the quality of our assets for the composition of its infrastructure investment fund, and we are happy to continue together on this journey,” says Marco Tanure, CFO of Sterlite Power Brazil.

This is the second transaction between the two companies. The Arcoverde Project, completed in 2019, with 129 km in transmission lines, three substations (a new one) in the Region of Pernambuco, was acquired by the fund in 2020. 

“The partnership involving Vineyards represents an important acquisition for Vinci Energia FIP-IE (VIGT11), which focuses on the electricity sector. This will be the seventh asset acquired by the fund and, currently, will represent a relevant portion of the fund’s portfolio. Vineyards reinforces the investment strategy of VIGT11 in high quality assets and high predictability of cash generation “, says José Guilherme Cruz Souza, partner and head of Infrastructure at Vinci Partners.”

About Sterlite Power

Sterlite Power is a leading global developer of power transmission infrastructure with projects in India and Brazil. In the country since 2017, the company has a relevant portfolio of 7 energy transmission projects in 9 states (Bahia, Ceará, Goiás, Pará, Paraíba, Minas Gerais, Rio Grande do Norte, Rio Grande do Sul and Sergipe), totaling 2.000 ckm in length and CAPEX of more than R $ 3.4 billion. Worldwide, the company offers solutions for upgrading and strengthening existing networks and is the market leader in power conductors, EHV, and OPGW cables. Sterlite Power has established industry benchmarks through high technologies and operational management that seek excellence in asset management.

For more details, please visit: www.sterlitepower.com/brwww.sterlitepower.com

Media: media@sterlite.com

RELATED PRESS RELEASE

Sterlite Power raises INR 725 Crores from GEF Capital and ENAM Holdings

Sterlite Power Strengthens Goa’s Energy Infrastructure with First 400 kV GIS Substation under the Goa-Tamnar Transmission Project Special Purpose Vehicle

Infravision and Sterlite Power Partner to Advance India’s Transmission Infrastructure with Cutting-Edge Technology-Enabled Construction Methods

SYSTEM AVAILABILITY

Projects DEC 2019 Availability since COD
ENICL 99.82 99.54
BDTCL 99.90 99.71
JTCL 100.00 99.54
RTCL 100.00 99.84
PKTCL 100.00 99.93
NRSS-XXIX 98.61 99.67
MTL 100.00 99.95
OGPTL 100.00 99.95
PTCL 100.00 99.94
KTL 100.00 100.00
GPTL 99.81 99.60