PROJECT STORY
During the planning phase of the project, we identified that the sheer number of crossings would prove to be a challenge. Getting clearances, approvals and ensuring ROW in the Maharashtra side of the line was critical, as we had faced obstacles in similar projects around the country. We also identified a stumbling block which could potentially stall the project in the execution phase – the type of soil in about 60 kms section of the line between Khandwa and Indore could not be worked on during the monsoon.
Our teams began obtaining clearances simultaneously from the various departments to ensure that previously faced ROW challenges could be easily overcome. We also broke the norm by attempting to construct the most challenging section first (between Khandwa and Indore) to ensure that work on the project would not be stalled during the monsoon.
This project will improve power supply and grid reliability by delivering 1320MW of thermal power from Khandwa to consumers in the domestic, commercial, agricultural, and industrial segments.
Project Detail
The project has 6 elements consisting of one pooling stations at 765/400 kV level of 3,000 MVA capacity and four transmission lines extending over ~626 circuit kilometers. The asset spans across Madhya Pradesh and Maharashtra and terminates in one end at the Dhule substation of BDTCL, IndiGrid’s subsidiary since IPO. The project is of strategic importance for evacuation of 1,320 MW of power generated by the Khargone Power Plant to 765 kV Khandwa substation to further distribute it downstream and will strengthen the power transmission network in the Central and Western India.
TIMELINES
Khandwa- Dhule 765 KV D/C TL
- State : Madhya Pradesh and Maharashtra
- Length: 191 Km
- Commissioning: Dec’2021
Khandwa- Indore 765 KV D/C TL
- State : Madhya Pradesh
- Length: 90 Km
- Commissioning: Feb’2020
Khandwa- Khargone 400 KV D/C TL
- State : Madhya Pradesh
- Length: 25 Km
- Commissioning: Feb2020
Khandwa 765 /400 KV Sub Station
- State : Madhya Pradesh
- Commissioning: Feb’2020
LILO at Khandwa
- State : Madhya Pradesh
- Length: 7 Km
- Commissioning: Dec’2018