Novo Estado

This project is the expansion of North-Southeast and North-Northeast interconnections. This is a part of the Belo Monte HPP energy flow solution.

PROJECT STORY

The Novo Estado Project has 1831 km of transmission lines to be built, the implementation of 1 new substation and the expansion of some substations in the region to be deployed in the state of Pará and Tocantins.

This project is expected to generate 5.560 direct / indirect jobs.

Project Detail

Length: 1,831 km
Power: 230 kv

TIMELINES

Preliminary Environmental license
Installation Environmental license

PROJECT GALLERY

RELATED LINKS

 MUMBAI URJA MARG LIMITED

GOA TAMNAR TRANSMISSION PROJECT LIMITED

LAKADIA VADODARA TRANSMISSION PROJECT LIMITED (LVTPL)

SYSTEM AVAILABILITY

Projects DEC 2019 Availability since COD
ENICL 99.82 99.54
BDTCL 99.90 99.71
JTCL 100.00 99.54
RTCL 100.00 99.84
PKTCL 100.00 99.93
NRSS-XXIX 98.61 99.67
MTL 100.00 99.95
OGPTL 100.00 99.95
PTCL 100.00 99.94
KTL 100.00 100.00
GPTL 99.81 99.60